Road Improvement Projects

Blue Lake Township has a 1.2 mill property tax for road construction and repair that was voted by the electorate in August of 2010 Election.  Using the funds generated by this tax the following work schedule was proposed for 2011 – 2019.  Twin Lake Rd. between Squaw Lake Rd. and Sunset Trail was paved in the summer of 2012 at a cost of $414,689.   In the summer of 2013 we repaved Twin Lake Rd. between Sunset Trail and the Township line at a cost of $67,636.  In 2014 we paved Eagle Lake Drive at a cost of $163,472.  In 2015 we graveled several roads and Chip Sealed West Blue Lake Rd.  In 2016 we hope to Chip-Seal several of our older paved roads.  In June of 2015 we had $141,536 in the Highway fund.

               Proposed Road work Schedule for 2011 – 2019

 

Year

Road

Work

Cost Est 2010

Actual Cost

2011

None

None

$0

 

2012

 

Twin Lake (Sunset Trail to Squaw Lake)

Prep & Pave

Done 2012

$384,000 (loan $100,000 Req.)

$414,689

2013

Twin Lake (Sunset Trail to Township Line)

Wedge & Cap

$70,200

$67,636

2014

Eagle Lake Dr. (West) and N. Eagle Lane

Prep & Pave

$103,435

 $163,472

2015

Beaver, Bedal, Bell, Blue Point, Camron Bridge,  Lakeview, East, Merril, N.Crooked, Sunburry

2 inches Gravel

$63,140

 $63,355

2016

E. Bass Lake, Gedman (West of new pavement), Little Twin

Repair & Chip Seal

$33,280

 $81,237.50 to be completed spring 2017

2017

Beaver, Bedal, Bell, Blue Point, Camron Bridge,  Lakeview, East, Merril, N.Crooked, Sunburry

2 inches Gravel

$63,140

 

2018

Sunset Trail (North of Twin Lake Rd.)

Wedge & Cap

$195,000

 

2015

West Blue Lake  Rd.

Repair & Chip Seal

$27,000

 $44,456

2019b

Sunset Trail (South of Twin Lake)

Wedge & Cap

$85,800

 

 Presented to the Kalkaska County Road Commission at their February 11, 2011 meeting.